County Voice

Cyclic works completed on A525

As part of a new initiative, the highways team recently carried out much needed drainage on the A525 all the way from Denbigh to Ruthin. 

The work involved highway drainage maintenance, verges sided, ditches excavated, and the highway swept. In recent years vegetation had grown into the channels and was covering a number of drainage outlets which were creating standing water and were a potential hazard. In the 10 days that the work took, all of these issues were addressed, and the plan now is to evaluate the cost and effectiveness to see if this initiative can be rolled out to other locations in the county.

Photos before the work took place

 

Photos during the work taking place

 

Photos after the work had been completed

 

Taylorfitch. Bringing Newsletters to life