St Peter's Square Programme of Works

Over the coming months, a series of carefully planned works will be carried out to complete the St. Peter’s Square public realm improvement scheme.

Over the coming months, a series of carefully planned works will be carried out to complete the St. Peter’s Square public realm improvement scheme. The following table provides an overview of the planned phases of work, including where and when each section will take place.

Traffic management systems and road closures are inevitable and will only be implemented where necessary to protect the public and Contractor’s workforce. Road closures during the Ruthin festival will be managed by the Contractor’s traffic management sub-contractors to ensure a co-ordinated approach.

All dates are indicative* and may be subject to change due to weather or programme adjustments, but every effort will be made to minimise disruption throughout the construction period.

Phase

Area

Dates (not closed for full period)

Phase 1

Well Street & area behind The Old Courthouse

3 March 2026 – 26 May 2026*

Phase 2

Market Street

26 May 2026 – 28 July 2026*

Phase 3

Castle Street / Upper Clwyd Street

28 July 2026 – 18 August 2026*

Phase 4

St. Peter’s Square

19 August 2026 – 16 October 2026*

Phase 5

Clock Tower

22 September – 6 November 2026*

Surfacing works are then planned to take place from 9 – 18 November 2026*.

Phase 1 - Well Street and area behind and around The Old Courthouse

Phase 2 - Castle Street

Phase 3 - St. Peter’s Square – East and West side around square and Market Street

Phase 4 - St. Peter’s Square – North side of square and junctions with roads off square

All resurfacing works are currently planned to be completed at night to minimise disruption.

Throughout the project, pedestrian access will be managed, temporary ramps will be provided for accessibility, clear signage and secure barriers will be in place. Any issues can be relayed to either the Public Liaison Officer RuthinEnquiries@obrconstruction.com or the Project Team corporateprogrammeoffice@denbighshire.gov.uk

We appreciate your patience and co-operation during the construction phase of this project.